|
| |
There are a number of options, and combinations thereof,
that would present a far more feasible solution to the situation. We must
encourage TVA to seriously look at them instead of taking the current route.
Energy Conservation and Green Resources
 | Other than the other proposals described in the scoping
document, TVA has done little to require their customers to reduce energy
usage. The Tennessee Legislature adapted a voluntary energy code based on
ASHREA 90.1/1980. Not only is this code outdated, it has not been enforced.
It is estimated that updated, enforced energy codes such as those mandated by
the Federal Government could reduce urban energy usage by as much as 40%.
Wouldn’t it be more feasible for TVA to invest in community education, and
encouraging local adaptation and enforcement of energy codes that to simply
cave in to the demands of big business and developers? |
 | Today in Murfreesboro, numerous large mall and car
dealership parking lots sit underneath burning lights in broad daylight, with
no repercussions to the property owners. Is this mentality why we are being
asked to make such huge sacrifices? |
Why were the more feasible options under consideration
so quickly abandoned?
 | The first alternative was to construct a new substation
in Brentwood. The project would require no additional transmission line
easements, as it’s close to the Pinhook-Davidson transmission lines that
are already in existence. Thus, it would have little effect on landowners. The
capital costs for this would be 8% less than the Rutherford proposal and 3%
less than the Pinhook proposal; however, the costs of possible power
losses during transmission makes this proposal cost about $3 more than the
Rutherford alternative solution. TVA argues that the line outages during
construction are constraints that would possibly delay construction
completion to 2011. This option was TVA’s first choice. |
 | The second alternative to the Rutherford line was to
expand the existing Pinhook substation. TVA’s argument against the Pinhook
expansion is the possibility of damaging control equipment in the
existing substation area, resulting in outages at the substation. This
solution would be about 3% more than the Brentwood alternative and 6% less
than the Rutherford alternative. Overall project costs are about $17 million
more than the Brentwood alternative and $20 million more than the Rutherford
alternative, but these are based on hypothetically damaged equipment. |
Does the Rutherford alternative cause harm to the environment?
 | Our option, the Rutherford alternative, involves the
most destruction of and construction on Greenfield sites, resulting in
greater environmental impacts as compared to the other two options. |
|